Superintendent of Schools |
Excel ProjectA very special thank you to the voters of the district that supported the Excel Project. Below is the tentative timeline: April 1 - September 1, 2008 Design Phase September 1 - March 1, 2009 State Department of Education Review and Final Approval. April 1, 2009 - May 31, 2009 Bidding Process June 2009 Award Bids June 25, 2009 Start Construction December 31, 2009 Project Completion. For more information, Call the District office, 387-3445 Ext. 1510 |